The Company has made it a priority to reduce its negative environmental impact in the regions where it operates as it expands production and makes use of the best available technologies to improve the efficient use of natural resources.



Plans for 2018 Results of the reporting period Plans for 2019 and the mid-term
Retrofitting, modernisation, outfitting, and technical measures in order to reduce the environmental impact
Lebedinsky GOK
  • Irrigation of the dusting areas at the tailings facility with a reinforcing solution of the DUSTBIND treating agent from small aircraft on 616 hectares
  • Dust suppression at over 338.4 hectares of open pit roads, tailings facilities and at the crushing and sorting plant with the Bischofite binding agent
  • Application of clay soil (using a hydro-mechanical system) to temporarily unused sections #2 and #3 of the tailings facility on 300 hectares (600,000 m3)
Mikhailovsky GOK
  • Retrofitting of the pelletising plant. Modernisation of the dust collection system at transhipment sites of open pellet warehouses CO-3-GR-8, CO-2-CO-6 (2018 stage – equipment installation)
OEMK
  • Retrofitting of the 5th and 6th cooling water circuits to ensure the simultaneous operation of five continuous casting machines (final stage, commissioning)
  • Installation of a suction system in the limestone screening unit
Ural Steel
  • Reconstruction of the suction system at the stock houses of Blast Furnaces No. 3 and 4 (drafting of design documentation, choice of equipment supplier)
All the plans were implemented in full, which made it possible to significantly improve the air quality both inside the enterprises and in nearby regions. All the measures that were carried out have proven to be effective. For more details, see the sections Material Resources Use, Emissions, Air Protection and Climate Strategy, and Water Consumption and Protection. Metalloinvest:
  • Measures to equip stationary emission sources
  • automatic measuring and recording tools for pollutant emissions and/or discharges;
  • technical equipment to record and transmit information about pollutant emission and/or discharge indicators.
  • Summarising the initial results of the retrofitting conducted in 2018
  • Completion of construction and installation work as part of the reconstruction of the granemite emulsion explosive component production facility
Construction of new facilities
Lebedinsky GOK
  • Construction of a landfill for industrial waste disposal
Construction of the landfill has commenced and will continue in the new reporting period Lebedinsky GOK
Landfill for industrial waste disposal: reconstruction of Landfill Area No. 3; construction of a 100-tonne weigh house
Reclamation and biodiversity maintenance
Lebedinsky GOK
  • Biological reclamation of a 25 hectare loose overburden dump pit
  • Biological reclamation of a 15.8 hectare tailings dam
  • Sanitary and hygienic reclamation of tailings dam levees
Planting of acacias on the territory of the loose dump pits and tailings dam contributed to more dust-forming surfaces For more details, see the section Maintaining Biodiversity Lebedinsky GOK
  • Monitoring the vegetation cover at the landfill site
  • Development of basic procedures for the comprehensive continuous tracking (monitoring) of the condition and changes in the ecosystem of the Yamskaya Steppe and its components
OEMK
  • Final (mining) reclamation of the landfill for the production and consumption waste of OEMK (2nd stage)
Certification
Certification for compliance with the ISO 50001 Energy management standard by Mikhailovsky GOK, Lebedinsky GOK, and Ural Steel All Metalloinvest enterprises have been certified for compliance with ISO 50001 Energy management Continual confirmation of compliance with environmental management systems
Confirmation of compliance with the environmental management systems External audits confirmed compliance of the environmental management systems / integrated management systems with the requirements of ISO 14001:2015
Improved environmental indicators
Continued work to reduce the environmental impact, including by modernising production facilities
  • Increased material reuse rate
  • Increased waste utilisation rate and reduced waste disposal rate
  • Reduced emissions of solid particles (dust) into the atmosphere
  • Introduction and modernisation of in-house generation technologies in order to reduce energy consumption and reduce energy consumption costs
For more details, see the sections Material Resources Use, Emissions, Air Protection and Climate Strategy, and Energy Consumption and Efficiency.
Metalloinvest:
  • Increased material resource reuse rate
  • Research work on reactive power compensation
Lebedinsky GOK:
  • Overall decrease in dust air pollution due to a reduction in dust-forming areas
OEMK:
  • Reduced negative environmental impact during the operation of the shot-blasting unit of the metal conditioning site and during the transportation of oxidised and metallised pellets
Ural Steel:
  • Decrease in harmful air pollutant emissions from emission sources of the blast furnace shop
Environmental strategy and planning
    Metalloinvest
  • Updating existing policies with provisions on how to interact with specially protected natural areas.
  • Developing measures to reduce direct greenhouse gas emissions and increase carbon capture.